FREQUENCY OF
INSPECTIONS.-Most manufacturers recommend complate inspections, external
and internal, at intervals of from 6 to 12 months. Experience has
shown that a considerable expense is involved, some of which maybe unnecessary,
in adhering to the manufacturer's recommendations of internal inspections at 6-
to 12-month intervals. With proper external checks,part of the expense, delay,
and labor of internal inspections may be avoided without sacrifice of
dependability.
Inspection
schedule for new breakers.- A temporary schedule of frequent inspections is
necessary after the erection of new equipment, the modification or
modernization of old equipment, or the replication of old equipment under
different conditions. The temporary schedule is required to Correct internal
defects which ordinarily appear in the first year of service and to correlate
external check procedures with internal conditions as a basis for more
conservative maintenance program there after. Assuming that a circuit breaker
shows no serious defects at the early complete inspections and no heavy
interrupting duty is imposed, the following inspection schedule is recommended:
6 months
after erection - Complete inspection and adjustment
12 months
after previous inspection- Complete inspection and adjustment
12 months
after previous inspection- Complete inspection and adjustment
12 months after previous inspection - External checks and inspection; if checks are satisfactory, no
internal inspection
12 months
after previous inspection - Complete inspection and adjustment
Inspection
schedule for existing breakers. - The inspection schedule should be based by
the interrupting duty imposed on the breaker. It is advisable to make a
complete internal inspection after the first severe fault interruption. If
internal conditions are satisfactory, progressively more fault interruptions
may be allowed before an internal inspection is made. average experience
indicates that up to five fault interruptions are allowable between inspections
on 230 kV and above circuit breakers, and up to 10 fault interruptions are
allowable on circuit breakers rated under 230 KV.Normally, no more than 2 years
should elapse between external inspections or 4 years between internal inspections.
EXTERNAL
INSPECTION GUIDE-LINES.- The following items should be included in an external
inspection of a high-voltage breaker.
Visually
inspect PCB externals and operating mechanism. The tripping latches should be
examined with special care since small errors in adjustments and clearances and
roughness of the latching surfaces may cause the breaker to fail to latch
properly or increase the force necessary to trip the breaker to such an extent
that electrical tripping will not always be successful, especially if the tripping
voltage is low. Excessive "opening" spring pressure can cause
excessive friction at the tripping latch and should be avoided. Also, some
extra pressure against the tripping latch may be caused by the electromagnetic
forces due to flow of heavy short-circuit currents through the breaker.
Lubrication of the bearing surfaces of the operating mechanism should be made
as recommended in the manufacturer's instruction book, but excessive
lubrication should be avoided as oily surfaces collect dust and grit and get
stiff in cold weather, resulting in excessive friction.
Check oil
dielectric strength and color for oil breakers. The dielectric strength must be
maintained to prevent internal breakdown under voltage surges and to enable the
interrupter to function properly since its action depends upon
changing the internal arc path from a fair conductor to a good insulator in the
short interval while the current is passing through zero. Manufacturer's
instructions state the lowest allowable dielectric strength for the various
circuit breakers. It is advisable to maintain the dielectric strength above 20 kV even though some
manufacturer's instructions allow 16 kV.
If the oil
is carbonized, filtering may remove the suspended particles, but the
interrupters, bushings, etc., must be wiped clean. If the dielectric strength
is lowered by moisture, an inspection of the fiber and wood parts is advisable
and the source of the moisture should be corrected. For these reasons, it is
rarely worthwhile to filter the oil in a circuit breaker while it is in
service.
Observe
breaker operation under load.
Operate
breaker manually and electrically and observe for malfunction. The presence of
excessive friction in the tripping mechanism and the margin of safety in the
tripping function should be determined by making a test of the minimum voltage
required to trip the breaker. This can be accomplished by connecting a switch
and rheostat in series in the trip-coil circuit at the breaker (across the
terminals to the remote control switch) and a voltmeter across the trip coil.
Staring with not over 50 percent of rated trip-coil voltage, gradually increase
the voltage until the trip-coil plunger picks up and successfully trips the
breaker and record the minimum tripping voltage. Most breakers. Should trip at
about 56 percent of rated trip-coil voltage. The trip-coil resistance should be
measured and compared with the factor test value to disclose shorted turns.
Most modern
breakers have trip coils which will overheat or burn out if left energized for
more than a short period. An auxiliary switch is used in series with the coil
to open the circuit as soon as the breaker has closed. The auxiliary switch
must be properly adjusted and successfully break the arc without
damage to the contacts.
Tests should
also be made to determine the minimum voltage which will close the breaker and
the closing coil resistance.
Trip breaker
from protective relays.
Check
operating mechanism adjustments. Measurements of the mechanical clearances of
the operating mechanism associated with the tank or pole should be made.
Appreciable variation between the value found and the setting when erected or
after the last maintenance overhaul is erected or after the last maintenance
overhaul is usually an indication of mechanical trouble. Temperature and difference
of temperature between different parts of the mechanism effect the clearances
some. The manufacturers' recommended tolerances usually allow for these
effects.
Double test bushings and breaker.
Table
I - Maximum Contact Resistance
Air
Circuit Breakers
KV AMPERES MICRO OHMS
5-15
600 100 Ohms
1200 50 Ohms
2000 50
Ohms
Oil Circuit Breakers :-
KV AMPERES
MICRO OHMS
7.2-15
600 300 Ohms
1200 150 Ohms
2000 75 Ohms
4000 40 Ohms
23- 24
ALL 500 Ohms
46 ALL 700 Ohms
69 600 500 Ohms
1200 500 Ohms
2000 100
Ohms
115-230 ALL 800 Ohms
Measure contact resistance. As long as
no foreign material is present,the contact resistance of high pressure,
butt-type contacts is practically independent of surface
condition.Nevertheless, measurement of the electrical resistance between
external bushing terminals of each pole may be regarded as the final
"proof of the pudding." Any abnormal increase in the resistance of
this circuit may be an indication of foreign material in contacts, contact
loose in support,loose jumper, or loose bushing connection. Any one of these
may cause localized heating and deterioration. The amount of heat above normal
may be readily calculated from the increase in resistance and the current.
Resistance of the main contact circuits
can be most conveniently measured with a portable double bridge (Kelvin) or a
"Ducter." The breaker contacts should not be opened during this test because
of possible damage to the test equipment.
Table 1 gives maximum contact resistances for typical classes of
breakers.
Fortunately, these difficulties are
most likely to appear early in the use of a breaker and would be disclosed by
the early internal inspections. As unsatisfactory internal conditions are
corrected and after one or two inspections show
the internal conditions to be satisfactory, the frequency of internal
inspections may safely be decreased.
INFLUENCE OF DUTY IMPOSED.-
Influence
of light duty.- Internal inspection of a circuit breaker which has had no
interruption duty or switching since the previous inspection will not be
particularly beneficial although it will not be a total loss. If the breaker
has been energized, but open, erosion in the form or irregular grooves (called tracking)
on the inner surface of the interrupter or shields may appear due to
electrostatic charging current. This is usually aggravated by a deposit of carbon
sludge which has previously been generated by some interrupting operation. If
the breaker has remained closed and carrying current, evidence of heating of
the contacts may be found if the contact surfaces were not clean, have
oxidized, or if the contact pressure was improper. Any shrinkage and loosening
of wood or fiber parts (due to loss of absorbed moisture into the dry oil) will
take place following erection, whether the breaker is operated or not.
Mechanical operation, however, will make any loosening more evident. It is
worthwhile to deliberately impose several switching operations on the breaker
before inspection if possible. If this is impossible, some additional information may be gained by operating the breaker several times
after it is deenergized, measuring the contact resistance of each pole initially
and after each operation.
Influence of normal duty.- The relative severity of
duty imposed by load switching, line dropping, and fault interruptions depends
upon the type of circuit breaker involved. In circuit breakers which employ an
oil blast generated by the power arc, the interruption of light faults or the interruption
of line charging current may cause more deterioration than the interruption of heavy faults within the rating
of the breaker because of low oil pressure. In some designs using this basic
principle of interruption, distress at light interrupting duty is minimized by multiple
breaks, rapid contact travel, and turbulence of the oil caused by movement of
the contact and mechanism. In designs employing a mechanically driven piston to
supplement the arc-driven oil blast, the performance is more uniform. Still more
uniform performance is usually yielded by designs which depend for arc
interruption upon an oil blast driven by mechanical means. In the latter types,
erosion of the contacts may appear only with heavy interruptions. The
mechanical stresses which accompany heavy interruptions are always more severe.
These variations of characteristic
performance among various designs must be considered when judging the need for
maintenance from the service records and when judging the performance of a
breaker from evidence on inspection. Because of these variations, the practice
of evaluating each fault interruption as equivalent to 100 no-load operations,
employed by some companies, is necessarily very approximate although it may be
a useful guide in the absence of any other information.
Influence of severe duty.-Erosion of
the contacts and damage from severe mechanical stresses may occur during large fault
interruption.The most reliable indication of the stress to which a circuit
breaker is subjected during fault interruptions is afforded by automatic
oscillograph records. Deterioration of the circuit breaker may be assumed to be
proportional to the energy dissipated in the breaker during the interruption.The
energy dissipated is approximately proportional to the current and the duration
of arcing; that is, the time from parting of the contacts to interruption of
the current.However, the parting of contacts is not always evident on the
oscillograms, and it is sometimes necessary to determine this from indicated
relay time and the known time for breaker contacts to part.Where automatic
oscillograph records are available, they may be as useful in guiding oil
circuit breaker maintenance as in showing relay and system performance.
Where automatic oscillographs are not
available, a very approximate, but nevertheless useful, indication of fault
duty imposed on the circuit breakers may be obtained from relay operation targets and accompanying system conditions.
All such data should be tabulated in the circuit breaker maintenance file.
This post is genius and can be applied to almost every other business' marketing plan. Thanks for the tips.
ReplyDeleteHv Testing Equipment