MAINTENANCE PROCEDURE FOR SUBSTATIONS AND SWITCHGEAR
The maintenance of the switchgear
and electrical equipment can be carried out safely and efficiently through the
following steps.
1.
Understanding
the job
2.
Availing
the permit to work
3.
Organizing
for the work
4.
Availing
the shut-down
5.
Maintenance
work
6.
Closing
the work
7.
Normalizing
power status
8.
Returning
the permit
9.
Record
results.
1.)
Understanding the job:
a)
The
Supervisory staff must have a clear idea about the job to be carried out in
detail and stepwise. They should have a fair idea of this job to their
subordinates.
SUBSTATIONS
RM01 TO RM13 MIANTENANCE OF 11 K. V./ 3.3K.V. TRANSFORMER
After
obtaining the work permit, check the tag number on the VCB Panel.
Request M-20
staff to trip and earth 11K.V. connected feeder with copy of the work permit.
M-20 staff
will place earthing truck in place of drawn out 11KV breaker.
Confirm that
M20 staff makes this earthing truck “ON” and then lock it using your own lock and
carry the key with you.
While going
back to your substation confirm that the transformer under maintenance has no
humming noise.
Check again
the YCB panel; it should be in off position. This confirms the operational
status of the inter-trip with M-20 feeder.
Rack-out
the YCB
Open the
cubicles, holds both handle and lift the latch and with sufficient force,
draw-out the breaker and the breaker can be drawn-out to its Test/Rack-out
position. At the correct position, the latch shall come back down to its position.
Switch off the
control supply and disconnect the control cable plugs. Remove stopper strip in
front of the VCB by unscrewing the nuts. Pressing two knobs to their handle
hooks, draw-out breaker completely out of panel.
Earth
the cable side of the incomer.
Insert the
earthing handle in its position, push the latch and operate.
Identification
of the job includes knowing location of the equipment, its function along with
its general characteristics such as voltage level, capacity, duty etc.
Alternate arrangement
should be considered and must be provided for continuity of power supply before
starting to avail shut down on the equipment.
Availing
Permit to Work
Permit to work
must be availed.
1.1.1.
By
a person competent to receive it.
1.1.2.
From
a person competent to issue it.
1.1.3.
For
a valid assigned and approved work.
1.1.4.
After
having explained to Operation staff details of steps of the work to be done.
1.1.5.
With
due intimation and signature of the KNPC.
Engineer in
case the work involves switching operation of any UPS system.
In case the work involves
probability of annunciation / alarm to any department other than operation,
i.e. Fire Station then such department should be informed accordingly about the
work prior to taking up such work.
Permit to work
must be readily available / displayed at the site of work to the inspecting
authorities.
Organizing
the work
Caution Notice
duly filled in and signed must be prominently displayed at the equipment
control panel under work and half portion of Caution Notice should be displayed
at the equipment.
Staff for the
maintenance work should be nominated and informed accordingly.
Equipment for
work must be identified by at least two senior supervisor staff for its
correctness before starting any work.
Cordon-off the
correct equipment with caution tape around.
Inter-relation
between the equipment under maintenance and that related to it by Power-flow or
process logic must be clearly understood by the person authorized to work. In
case of any doubt, seniors must be consulted till satisfactory clarification.
Availing
shut-down
Check the
prevailing status of the Power-flow before starting any work, its total load in
case of parallel Operations of the Transformers and the status of the Bus-tie.
Just before
availing shut down, inform Operations staff (and Fire Station if required)
about your steps of operation and theirs expected alarms and changes in Power –
flow.
Switch – off
the circuit Breaker after confirming the tag number, this operation should be
done by the authorized person who avail the work permit and in the presence of
the area engineer.
Rack-out the
circuit Breaker.
Earth the
circuit as per manufacturer procedure and using the proper tools.
MAINTENANCE
WORK
Allocate the
job to certain staff whom should be only allowed to be present at he site.
Carry out the
required maintenance for the equipment as per the CMMS and the manufacturer
recommendations.
Closing
Down Maintenance Work.
Remove
cordon-tape around the equipment (if applicable).
Clean the
site.
Declare to
your staff that the work is completed.
Normalizing
the system.
Remove the
circuit earthing as per the approved procedure after checking he tag number.
Rack – in the
circuit breaker as per the approved procedure.
Returning
permit to work.
Inform
Operation staff that the work is completed.
Operate the
earthing handle downward using sufficient force. The earthing switch will
operate making the incoming cable earthed.
Observe and
check correctness of indications i.e. VCB OFF condition Earth Switch ON
condition.
Lock the
cubical compartment.
Maintenance
of the transformer.
Allocate this
job to certain staff whom will be only allowed to enter the transformer yard.
Clean
externally the body of transformer starting from the top downwards, watching
for any damage, oil leakage etc.
Open up
primary and secondary side cable box covers. Open also the neutral C.T. Box
cover and clean them all.
Check for any
spark – pitting or looseness of connections and if so, rectify.
Check and
clean all earthing connections and refit them.
Check the
condition of the silica gel and, if necessary, replace it along with necessary
oil quantity.
Clean and
check the control panel for the cooling system of the transformer for manual
operation of the fans.
Megger the
transformer as under:
1.
Making
earthing truck at M-20 S/S “OFF”.
2.
Switch
“OFF” the 3.3KV side earthing switch.
3.
Megger
11 KV to transformer body and note down results.
4.
Measure
insulation resistance values’ of primary and secondary
5.
Sign
in column no.9 for having completed the work. See that all copies have this
signature.
6.
Confirm
that operators signature is obtained on all three copies for having agreed that
the work has been completed.
7.
Take
away your copy of the permit to work.
Recording
the results
1.
Record the job done in the substation log book
2.
Make entries in the history card file about the maintenance work done and
sign it.
For primary to
earth and primary to secondary use 5KV megger.
For secondary
to earth use 2.5KV megger.
Close the
terminal boxes and ensure no tools, materials left inside.
Take
transformer oil (testing of dielectric strength and acidity) samples.
Position the
lifting trolley of potential transformer near the P.T. cubicle. Lift the
latching pin on P.T. handle on both sides, pull out outward. Lock it in
trolley. Remove control plug pins. Pull out and place it on floor.
Position the
same trolley near lightning arrestor cubicle. Lift the locking pins on L.A.
handles, pull outward. Lock it in trolley and pull out.
Clean P.T
& L.A., tighten connection, and check for abnormality. Measure insulation
resistance values (2.5 KV megger).
Rack – in P.T.
& L.A. following same procedure.
Clean VCB,
lubricate all moving parts, and check for manual operation, clearance of contacts.
Measure contact resistance and insulation values of poles.
Insert VCB in
test position. Replace stopper flap in its original position. Connect control
plug pins to VCB and switch on control supply.
Carry out
functional tests.
a)
Inter
trip
b)
Buchholzs
relay trip alarm
c)
Winding
temperature and oil level alarms.
Closing
down maintenance work.
1.
Remove
cordoning-off tape around the transformer.
2.
Confirm
that transformer yard has danger warning signs in their proper place.
3.
Clean
the transformer yard.
4.
Ask
everybody to go out of transformer yard and lock the yard from outside.
5.
Calibrate
the measuring and protecting instruments with KNPC approval and record results.
6.
Declare
orally to all that the work is completed.
Normalizing
the system
1.
Return
the key and open lock of earthing truck in M-20 S/S.
2.
Request
M-20 S/S staff to remove earthing truck and insert 11 KV VCB in service
position.
3.
Request
M – 20 staff to make concerned 11 KV feeders VCB ON.
4.
Check
the humming noise of this transformer is audible.
5.
Checks
from the panel that correct values o voltage are available.
6.
Close
3.3KV breaker of the transformer.
7.
Check
the load shared by this transformer with previous values and that of the other
transformer.
Returning
permit to work
Inform
operation staff that the work is completed.
Sign in column
no.9 for having completed the work. See that all 3 copies have this signature.
Confirm that
operator’s signature is obtained on all three copies for having agreed that the
work has been completed.
Take away your
copy of the permit to work.
Recording
the Results
Make entries
in the history card file about the maintenance work done, sign it.
Obtain oil
sample results and study them. Also enter this result in the history file.
I would like to your explaination about this blog. Very fantastic. You can also refer to us 11KV VCB Manufacturers see this for more information.
ReplyDeleteThank you for Posting And sharing such great information.
ReplyDeletePower transformers in India | Transformer manufacturer in India
Hello friends, here we have an information for you about the purchasing of laboratory instruments. If you are planning to set up the laboratory, then Atico Export is a perfect choice for you. By visiting the www.aticoexport.com, you can check out the entire range of instruments and mail your specifications as per your requirement.
ReplyDeleteHello friends, are you looking for the manufacturer or supplier of scientific lab instruments, then we have a best option for you. Atico Export is a place from where you can order the best quality instruments on affordable prices. For more information click on www.aticoexport.com.
ReplyDeleteMost valuable and fantastic blog I really appreciate your work which you have done about the Transformer,many thanks and keep it up.
ReplyDeleteTransformer