CONTACTORS:
Contactor
is a mechanical switching device capable of making carrying and breaking
electric current under normal circuit conditions including operation overload
conditions.
Contactors have a main circuit and control circuit. The
contactors are designed according to the method of energizing the control
circuit, namely Elector Magnetic, Pneumatic, and Electro-Pneumatic.
AC-3 Duty – Squirrel – cage induction motor: Starting,
Switching off.
OVERLOAD RELAY
SETTING:
Overload protection given for almost all motors. The overload
relay setting will be of 110% in general.
STARTING CURRENT:
Starting current of a induction motor generally will be 6 times the rated
current.
FAULT EXPERIENCED:
Individual’s experience.
SINGLE PHASING:
One
of the supply lines gets disconnected due to rupturing of fuse or open circuit
in one of the three supply connection. In such cases the motor continues to run
on a single phase supply of 440V. If the Rotor is locked to its rated full
load, it will draw excessive currents on single phasing. The windings get
overheated and damage is caused.
LOCKED ROTOR
CURRENT: Due to mechanical overload in motor locked, rotor can sometimes
happen and during this time the motor will draw the maximum current equal to
the starting current. This is called the Locked rotor current.
STARTING TIME:
The time taken for a motor form starting to attain its full speed is called the
starting time. It will be generally 4 to 5 seconds for small and medium range
motors and 8 to 10 seconds for large motors.
UNDER VOLTAGE
CONDITIONS: Under voltage conditions in a motor greatly affect its
performance. During this condition, the motor speed reduce it will draw more
current and this will cause rise in temperature of windings. For protecting the
motor from this condition, under voltage release is provided.
OVERLOAD RELAY
TESTING:
The characteristics of the relay should be selected and set to
suit the protection requirement of particular motor, as the thermal time
constant for the motor can vary wildly (15 minutes to 1 hour) curve A indicates
characteristic of motor heating to reach maximum permissible temperature in 15
minutes for moderate overload (1.3 times full load currents). The relay will
trip according to characteristics ‘B’ for overload of 200% the relay will in
less than 4 minutes, motor can with stand 200% overload for 4 minutes.
PUSH BUTTON
STATIONS:
These are installed in the units near each motor for starting and
stopping. The control supply for the stations is 110DC feeding from the
respective switch gears or 230V A.C.
GREASING INTERVAL:
The bearings of motor shall be greased according to the recommended interval
and quantity, by the manufacturer, example Greasing interval – 1500 running
hours. Quantity is 20grms.
MEGGER VALUE:
The insulation resistance value of the winding of the motor shall be checked
periodically during Preventive maintenance.
For 3.3 KV motor, the IR value shall
be checked with 1 KV megger.
For 11 KV
motor, the IR value shall be checked with 5 KV megger.
WINDING RESISTANCE:
The
winding resistance of the motor shall be checked during preventive maintenance
with the bride. The winding resistance of the three windings should be equal.