OIL AND GAS,PETROCHEMICALS AND POWER PLANT ENGINEERS AND TECHNICIANS INTERVIEW QUESTION AND ANSWERS FOR ELECTRICAL AND INSTRUMENTATION ENGINEERING
Sunday, August 25, 2013
UPS
UPS
The circuit drawn pertains to a regular industrial UPS (Uninterruptible Power Supply), which shows how the batteries take control during an outage in electrical supply or variation beyond the normal limits of the voltage line, without disruption on the operation providing a steady regulated output (5 Volts by LM7805) and an unregulated supply (12 Volts).
The input to the primary winding of the transformer (TR1) is 240V. The secondary winding can be raised up to 15 Volts if the value is at least 12 Volts running 2 amp. The fuse (FS1) acts as a mini circuit breaker for protection against short circuits, or a defective battery cell in fact. The presence of electricity will cause the LED 1 to light. The light of LED will set off upon power outage and the UPS battery will take over
The circuit was designed to offer more flexible pattern wherein it can be customized by using different regulators and batteries to produce regulated and unregulated voltages. Utilizing two 12 Volt batteries in series and a positive input 7815 regulator, can control a 15V supply.
Industrial UPS are generally categorized as:
Standby – battery backup and surge protection
Line Interactive – variable-voltage transformer and regulates the input AC voltage
Online – supplies all or at least a part of the output power
Thursday, August 8, 2013
3300 / 440V TRANSFORMER MAINTENANCE PROCEDURE
HTCB – VCB
(TOSHIBA MAKE) LTCB
– ACB (TOSHIBA MAKE)
1.
Obtain
work permit from operations for the required transformer with proper tag
number.
2.
Check
all the parameters on both HV/LV side and both LV & HV are closed. Check
both transformers are in service.
3.
Prepare
caution notice/permit to work and display it on HV & LV panels.
4.
Switch
off LV side breaker (ACB), and then switch
off HV side breaker (ACB) of current tag number. Make sure that there is no
power interruption.
5.
Open
the HT breaker panel. Lift the latch pin upward on both the handles pull the
breaker outward from service position to test position.
6.
Switch
off control supply and remove control plugs and the front o ‘CB’. Remove the
stopper plate, pull the VCB outside
breaker compartment
7.
Open
LV (ACB) breaker panel.
8.
Lift
the flapper (Middle of breaker – right hand side) upward and insert rack out/in
handle into the slot.
9.
Rotate
the handle anti-clockwise till it reaches disconnected position. Pull the ACB
outward after lifting the stopper levers on both sides of ACB
10. Position the trolley carrier and move
it inside, below the lifting pins or both sides of ACB. Lift the trolley upward
will it carries breaker. Pull the trolley outside and place the breaker on
floor.
11. Release charged spring by manually
operating on/off of VCB and ACB.
12. Put the earthing hand le of 3.3 KV
side earthing switch compartment which is above VCB cubicle.
13. Slide the stopper plate towards right
hand side, lift earthing leaver and release the stopper plate.
14. Remove the castle key from ACB,
insert in the earthing breaker operate the key to release the locking pin.
15. Insert the rack-in handle to the slot
(right side) and turn it clockwise if it reaches service position.
16. Remove handle and switch on control
supply of earthing switch.
17. Close panel door and turn earthing
switch on. Observe earthing indication.\provide barrier caution tape on both
sides of transformer of correct tag number.
18. Clean whole transformer. Open LV
& HV side terminal boxes. Inspect and tighten terminations hi-speed
bushings.
19. Clean and tighten all earthing
connections.
20. Measure insulation resistance of
primary and secondary windings with earth and between windings. For HT winding
use 2.5KV megger. For LV winding use 500V megger. Remove LT side neutral link
before meggering.
21. Close the terminal boxes. Check inert
gas pressure. Take transformer oil for testing.
22. Clean, check and inspect VCB and ACB
for looseness and any abnormality. Apply petroleum jelly for finger contacts.
Megger insulation resistance values of terminals. Measure contact resistance of
poles.
23. Check manual operations of ACB and
VCB.
24. Insert VCB in breaker compartment up
to test position. Put back the stopper flap in position. Make sure breaker is
off plug in control pin plugs and switch on control supply.
25. Rack out earthing breaker to
disconnected position on LV side. Take out the castle key.
26. Insert the ACB using trolley and rack
– in by turning rack – in handle clockwise to service position.
27. Perform functional test by operating
protective devices.
28. Push both breakers to service
position. Switch on HT breaker. Observe voltage.
29. Close LT breaker. Observe voltage and
current on both HT & LT sides.
30. Remove caution tags and cancel
permit.
31. Enter rack – in / rack – out details
in substation log book.
32. Record all readings and values in
history cards.
33. Send oil samples for testing acidity
and dielectric strength.
Wednesday, August 7, 2013
MAINTENANCE PROCEDURE FOR SUBSTATIONS AND SWITCHGEAR
MAINTENANCE PROCEDURE FOR SUBSTATIONS AND SWITCHGEAR
The maintenance of the switchgear
and electrical equipment can be carried out safely and efficiently through the
following steps.
1.
Understanding
the job
2.
Availing
the permit to work
3.
Organizing
for the work
4.
Availing
the shut-down
5.
Maintenance
work
6.
Closing
the work
7.
Normalizing
power status
8.
Returning
the permit
9.
Record
results.
1.)
Understanding the job:
a)
The
Supervisory staff must have a clear idea about the job to be carried out in
detail and stepwise. They should have a fair idea of this job to their
subordinates.
SUBSTATIONS
RM01 TO RM13 MIANTENANCE OF 11 K. V./ 3.3K.V. TRANSFORMER
After
obtaining the work permit, check the tag number on the VCB Panel.
Request M-20
staff to trip and earth 11K.V. connected feeder with copy of the work permit.
M-20 staff
will place earthing truck in place of drawn out 11KV breaker.
Confirm that
M20 staff makes this earthing truck “ON” and then lock it using your own lock and
carry the key with you.
While going
back to your substation confirm that the transformer under maintenance has no
humming noise.
Check again
the YCB panel; it should be in off position. This confirms the operational
status of the inter-trip with M-20 feeder.
Rack-out
the YCB
Open the
cubicles, holds both handle and lift the latch and with sufficient force,
draw-out the breaker and the breaker can be drawn-out to its Test/Rack-out
position. At the correct position, the latch shall come back down to its position.
Switch off the
control supply and disconnect the control cable plugs. Remove stopper strip in
front of the VCB by unscrewing the nuts. Pressing two knobs to their handle
hooks, draw-out breaker completely out of panel.
Earth
the cable side of the incomer.
Insert the
earthing handle in its position, push the latch and operate.
Identification
of the job includes knowing location of the equipment, its function along with
its general characteristics such as voltage level, capacity, duty etc.
Alternate arrangement
should be considered and must be provided for continuity of power supply before
starting to avail shut down on the equipment.
Availing
Permit to Work
Permit to work
must be availed.
1.1.1.
By
a person competent to receive it.
1.1.2.
From
a person competent to issue it.
1.1.3.
For
a valid assigned and approved work.
1.1.4.
After
having explained to Operation staff details of steps of the work to be done.
1.1.5.
With
due intimation and signature of the KNPC.
Engineer in
case the work involves switching operation of any UPS system.
In case the work involves
probability of annunciation / alarm to any department other than operation,
i.e. Fire Station then such department should be informed accordingly about the
work prior to taking up such work.
Permit to work
must be readily available / displayed at the site of work to the inspecting
authorities.
Organizing
the work
Caution Notice
duly filled in and signed must be prominently displayed at the equipment
control panel under work and half portion of Caution Notice should be displayed
at the equipment.
Staff for the
maintenance work should be nominated and informed accordingly.
Equipment for
work must be identified by at least two senior supervisor staff for its
correctness before starting any work.
Cordon-off the
correct equipment with caution tape around.
Inter-relation
between the equipment under maintenance and that related to it by Power-flow or
process logic must be clearly understood by the person authorized to work. In
case of any doubt, seniors must be consulted till satisfactory clarification.
Availing
shut-down
Check the
prevailing status of the Power-flow before starting any work, its total load in
case of parallel Operations of the Transformers and the status of the Bus-tie.
Just before
availing shut down, inform Operations staff (and Fire Station if required)
about your steps of operation and theirs expected alarms and changes in Power –
flow.
Switch – off
the circuit Breaker after confirming the tag number, this operation should be
done by the authorized person who avail the work permit and in the presence of
the area engineer.
Rack-out the
circuit Breaker.
Earth the
circuit as per manufacturer procedure and using the proper tools.
MAINTENANCE
WORK
Allocate the
job to certain staff whom should be only allowed to be present at he site.
Carry out the
required maintenance for the equipment as per the CMMS and the manufacturer
recommendations.
Closing
Down Maintenance Work.
Remove
cordon-tape around the equipment (if applicable).
Clean the
site.
Declare to
your staff that the work is completed.
Normalizing
the system.
Remove the
circuit earthing as per the approved procedure after checking he tag number.
Rack – in the
circuit breaker as per the approved procedure.
Returning
permit to work.
Inform
Operation staff that the work is completed.
Operate the
earthing handle downward using sufficient force. The earthing switch will
operate making the incoming cable earthed.
Observe and
check correctness of indications i.e. VCB OFF condition Earth Switch ON
condition.
Lock the
cubical compartment.
Maintenance
of the transformer.
Allocate this
job to certain staff whom will be only allowed to enter the transformer yard.
Clean
externally the body of transformer starting from the top downwards, watching
for any damage, oil leakage etc.
Open up
primary and secondary side cable box covers. Open also the neutral C.T. Box
cover and clean them all.
Check for any
spark – pitting or looseness of connections and if so, rectify.
Check and
clean all earthing connections and refit them.
Check the
condition of the silica gel and, if necessary, replace it along with necessary
oil quantity.
Clean and
check the control panel for the cooling system of the transformer for manual
operation of the fans.
Megger the
transformer as under:
1.
Making
earthing truck at M-20 S/S “OFF”.
2.
Switch
“OFF” the 3.3KV side earthing switch.
3.
Megger
11 KV to transformer body and note down results.
4.
Measure
insulation resistance values’ of primary and secondary
5.
Sign
in column no.9 for having completed the work. See that all copies have this
signature.
6.
Confirm
that operators signature is obtained on all three copies for having agreed that
the work has been completed.
7.
Take
away your copy of the permit to work.
Recording
the results
1.
Record the job done in the substation log book
2.
Make entries in the history card file about the maintenance work done and
sign it.
For primary to
earth and primary to secondary use 5KV megger.
For secondary
to earth use 2.5KV megger.
Close the
terminal boxes and ensure no tools, materials left inside.
Take
transformer oil (testing of dielectric strength and acidity) samples.
Position the
lifting trolley of potential transformer near the P.T. cubicle. Lift the
latching pin on P.T. handle on both sides, pull out outward. Lock it in
trolley. Remove control plug pins. Pull out and place it on floor.
Position the
same trolley near lightning arrestor cubicle. Lift the locking pins on L.A.
handles, pull outward. Lock it in trolley and pull out.
Clean P.T
& L.A., tighten connection, and check for abnormality. Measure insulation
resistance values (2.5 KV megger).
Rack – in P.T.
& L.A. following same procedure.
Clean VCB,
lubricate all moving parts, and check for manual operation, clearance of contacts.
Measure contact resistance and insulation values of poles.
Insert VCB in
test position. Replace stopper flap in its original position. Connect control
plug pins to VCB and switch on control supply.
Carry out
functional tests.
a)
Inter
trip
b)
Buchholzs
relay trip alarm
c)
Winding
temperature and oil level alarms.
Closing
down maintenance work.
1.
Remove
cordoning-off tape around the transformer.
2.
Confirm
that transformer yard has danger warning signs in their proper place.
3.
Clean
the transformer yard.
4.
Ask
everybody to go out of transformer yard and lock the yard from outside.
5.
Calibrate
the measuring and protecting instruments with KNPC approval and record results.
6.
Declare
orally to all that the work is completed.
Normalizing
the system
1.
Return
the key and open lock of earthing truck in M-20 S/S.
2.
Request
M-20 S/S staff to remove earthing truck and insert 11 KV VCB in service
position.
3.
Request
M – 20 staff to make concerned 11 KV feeders VCB ON.
4.
Check
the humming noise of this transformer is audible.
5.
Checks
from the panel that correct values o voltage are available.
6.
Close
3.3KV breaker of the transformer.
7.
Check
the load shared by this transformer with previous values and that of the other
transformer.
Returning
permit to work
Inform
operation staff that the work is completed.
Sign in column
no.9 for having completed the work. See that all 3 copies have this signature.
Confirm that
operator’s signature is obtained on all three copies for having agreed that the
work has been completed.
Take away your
copy of the permit to work.
Recording
the Results
Make entries
in the history card file about the maintenance work done, sign it.
Obtain oil
sample results and study them. Also enter this result in the history file.
OIL FIELD CABLES
A. 0.75, 1.5, 2.5, 4, 6, 10, 16, 25, 35, 50, 70, 95, 10,
150, 185, 240, 300, 400, 600,
(Dimensions are in Square mm).
Q. What is the use of cable gland?
A.
Cable glands
are used to protect against mechanical damages o cables during entering in
junction box, MCC etc. it also give earth continuity of cable Armor and
equipment body.
Q. What type of Cable gland used in
Oil Field?
A.
In explosion
proof areas double compression glands are used to avoid the gasses entering in
the electrical apparatus.
Q. What are the Cables used in Oil
Field?
A.
PVC – Poly Vinyl Chloride
XLPE
– Cross Linked Poly Ethylene
LC – Lead Covered
SWA – Steel Wire Armoured
PILC – Paper Insulated Lead Covered
MICC – Mineral Insulated Copper
Conductor
Q. What is MICC? Where it is used?
What mineral used in this cable?
A. Mineral Insulated Copper Conductor and it is used for
fire alarm systems and Lightings systems at Hazardous area without using
conduits and Magnesium oxide is used as mineral.
Q. What types of Cable joint and
termination kits used?
A. Cold Compound joint kits. Hot Compound joint kits and
Heat Shrinkable joint kits,
Hot Compound Termination and Heat
Shrinkable Termination kits,
Q. What is ferrule and where is used?
A. Ferrule is used to connect two conductors during
jointing. Three types are Crimping Type and Soldering Type for High Voltage
Cables as well as for Medium Voltage Cables and for Low voltages ferrules are
PVC Insulated.
Q. Why Lead Covered Cables are used
in Oil Fields?
A. Lead Covered Cables are used in Oil Fields due to
avoid damages of PVC Insulation, by hydrocarbon gases and chemical corrosion.
Q. How many types of lugs are used?
A. Crimping type and Soldering type lugs are used for
cable terminations.
Q. How to check the cable fault?
A.
As follows:
·
Isolate
the cable
·
Megger
the cable
·
Trace
the cable fault through cable fault locator and cable route through cable route
locator
·
If
the cable resistance is high use the burnout test kit
Before cutting the cable use spiking gun for safety
ILLUMINATION
ILLUMINATION:
The illumination is defined as the luminous
flux received per unit area.
Mathematical
illumination = Luminous flux / area = lumens/m2
INCADESCENT LAMP:
The lamps consist of an evacuated
glass bulb or gas filled having fine metallic wire within it. The filament
material normally used is tungsten. Titanium and Carbon also used for filament.
The filament should have the following properties.
1. Melting
point should be high
2. Vapor
pressure and temp coefficient should be low
3. Material
should be ductile and mechanically strong enough to bear vibration during use
Tungsten filament lamps have an average life of100 hour
under normal conditions.
SODIUM VAPOUR LAMP:
This type of lamp is of low
luminosity, so the length of this lamp is large. To get the required length it
is made in the form of a ‘U’ tube. Two
oxide coated electrodes are sealed into the ends. The tube contains a little
sodium and neon gas. The U tube is enclosed in a double walled vacuum flask to
keep the temperature within working range. Before the lamp starts working sodium
is in the form of a solid deposited on the side of tube walls. In the beginning
it operates as a low pressure neon lamp with pink colour. The lamp gets warm,
sodium is vaporized and it radiates yellow light and after about 10-15 minutes,
the lamp starts giving full light.
Subscribe to:
Posts (Atom)